Elina Premium, Hadapsar
by Binawat Realty LLP. Hadapsar, Pune 411028. View on Google Maps
- Launched
- 3 years 6 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 40 of 8050% booked
Project facts
| 2 BHK | 80 |
|---|---|
| Total units | 80 |
| Buildings | 1 |
| Land | 1.3 acres |
| Landowner share | 29 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 24 → 40 · final finishes 0% → 50%
Compared with 4 similar projects in PIN 411028
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 6 mths | 3 yrs 11 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | December 2026 | December 2026 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 50% | 92% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Paradise - B2 and B3 | March 2023 | June 2026 | 100% | 79 of 88 booked (90%) |
| Aura North | March 2023 | December 2027 | 30% | 1 of 40 booked (3%) |
| Kumar Pebble Park Joy 1 - C1 | January 2023 | December 2026 | 100% | All 56 units booked |
| Kumar Pebble Park Joy 2 - C2 | January 2023 | December 2026 | 100% | 52 of 56 booked (93%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 40 | |
| 100% | 100% | 0% | 24 | |
| 100% | 100% | 0% | 20 | |
| 100% | 60% | 0% | 8 | |
| 100% | 40% | 0% | 3 |
"—" means MahaRERA shows no figure for that update.
About this project
Elina Premium (MahaRERA P52100051205) is a residential project by Binawat Realty LLP in Hadapsar, Pune 411028. It was launched in June 2023. It has 80 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
40 of its 80 units are booked (50%). Since the December 2025 update, 16 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.