Skip to main content
← Back

Kumar Pebble Park Joy 1 - C1, Hadapsar

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Kumar Properties and Promoters Private Limited. Hadapsar, Pune 411028. View on Google Maps

Launched
3 years 11 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stage
Units booked
All booked56 units booked
Price per sq ft (incl. balconies and terrace)
₹7,2002024 · 11 sales80% of the 2024 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK56
Total units56
Buildings1
Land0.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: final finishes 81% → 100%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
730 – 750 sq ft₹52 – 54 lakh

Based on flats sold in 2024.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹7,200 per sq ft11 sales

Rate vs other Hadapsar projects, 2024: about 20% lower

Compared with 3 similar projects in PIN 411028

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411028
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths3 yrs 6 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)December 2026June 2027
Concrete structure (RCC) complete100%100%
Share of units booked100%50%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 9 months of the promised 3 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 71%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 81%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%56
100%100%81%56
100%100%0%56
100%71%0%56
100%0%0%36

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Kumar Pebble Park Joy 1 - C1 (MahaRERA P52100048543) is a residential project by Kumar Properties and Promoters Private Limited in Hadapsar, Pune 411028. It was launched in January 2023. It has 56 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

All 56 units are booked. 80% of the 2024 sales we found here were at ₹7,200 per sq ft or less, counting balconies and terrace in the size, based on 11 registered sales. Buyers here paid a rate about 20% lower than at other Hadapsar projects in 2024. Most buyers paid ₹52–54 lakh for flats of 730–750 sq ft.

Kumar's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA82
Completed without extending the possession date42
Completed after an extension, or lapsed5
Under construction35
Possession date extended by the builder5
Typical time from launch to 100% structure2 years 6 months
Complaints on MahaRERA, all Kumar projects71 (8 of 82 projects)

See all Kumar projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100048543.Check it on MahaRERA (P52100048543)All projects in Hadapsar, Handewadi