Nyati Emerald, Baner

by Nyati Builders Private Limited. Baner, Pune 411045. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Feb 2027 – Aug 2028varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
74%Mid-construction0 of 3 phases with structure completeWeighted across 3 phases
Units booked
867 of 1,17774% booked
Price per sq ft
₹11,7002026 salesup 4% on 2025See what buyers paid

Project facts

1 BHK144
2 BHK490
3 BHK488
Total units1,177
Buildings15
Land15 acres
Phases3
MahaRERA complaints (filed by or against the builder)2

Since Dec 2025: booked 821 → 867

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 840 sq ft₹92 lakh – ₹1.01 crore2026 sales
3 BHKabout 1,210 sq ft₹1.34 – 1.43 crore2026 sales

Price per sq ft, year by year

2023₹10,000 per sq ft
2024up 7% on 2023₹10,700 per sq ft
2025up 6% on 2024₹11,300 per sq ft
2026up 4% on 2025₹11,700 per sq ft

Registered sales across all 3 phases.

Compared with the typical Baner rate in 2026: about 15% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Nyati Emerald I
Mid-construction
P5210005123569695%81%
Nyati Emerald II
Mid-construction
P5210005485714479%89%
Nyati Emerald III
Mid-construction
P5210005506628220%46%
Show updates by phase

Nyati Emerald I (P52100051235)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%4%590
100%95%4%571
100%56%0%518
100%26%0%396
94%0%0%54

"—" means MahaRERA shows no figure for that update.

Nyati Emerald II (P52100054857)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%0%143
100%52%0%132
100%0%0%15

"—" means MahaRERA shows no figure for that update.

Nyati Emerald III (P52100055066)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
86%20%0%134
86%0%0%118
86%0%0%14
86%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Nyati Emerald is a project by Nyati Builders Private Limited in Baner, Pune 411045, registered with MahaRERA as 3 phases (P52100051235, P52100054857, P52100055066). The first phase was launched in June 2023. Together the phases have 1,177 units in 15 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from February 2027 to August 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 74% complete and final finishes 2% complete. 0 of the 3 phases have their structure complete.

867 of the 1,177 units reported for sale are booked (74%). In 2026 registered sales, 80% of flats here sold at ₹11,700 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 15% lower than the typical Baner rate in 2026. Most buyers paid ₹92 lakh–₹1.01 crore for 2 BHK flats of about 840 sq ft (2026 sales); ₹1.34–1.43 crore for 3 BHK flats of about 1,210 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Nyati's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA48
Completed without extending the possession date24
Completed after an extension3
Lapsed9
Under construction12
Possession date extended on the builder's application6
Typical time from launch to 100% structure2 years 1 month
MahaRERA complaints (filed by or against the builder), all Nyati projects32 (14 of 48 projects)

See all Nyati projects →

Source: MahaRERA registrations P52100051235, P52100054857 and P52100055066.Open MahaRERA and search P52100051235All projects in Baner, Balewadi, Mahalunge