Landson Shine, Chikhali
by Landson Properties. Chikhali, Pune 412114. View on Google Maps
- Launched
- 3 years 6 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 119 of 15079% booked
Project facts
| 2 BHK | 150 |
|---|---|
| Total units | 150 |
| Buildings | 1 |
| Land | 0.8 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 90 → 119 · structure 65% → 100% · final finishes 0% → 50%
Compared with 6 similar projects in PIN 412114
Projects with 70–300 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 6 mths | 3 yrs 2 mths |
| Possession date extended | No | 4 of 6 |
| Possession date (MahaRERA) | December 2026 | December 2027 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 79% | 56% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nexus Kinaara A | June 2023 | April 2028 | 100% | 89 of 180 booked (49%) |
| Aksha Vrundavan III | June 2023 | December 2027 | 100% | 110 of 236 booked (47%) |
| Krystal One Phase III | February 2023 | December 2026 | 100% | All 152 units booked |
| Aishwaryam Courtyard Gold | January 2023 | December 2028 | 71% | 250 of 476 booked (53%) |
| Prosperia Part 2 | January 2023 | December 2027 | 100% | 168 of 282 booked (60%) |
| Krystal One Phase II | October 2022 | August 2026 | 100% | All 112 units booked |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 119 | |
| 100% | 65% | 0% | 90 | |
| 100% | 0% | 0% | 44 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Landson Shine (MahaRERA P52100051650) is a residential project by Landson Properties in Chikhali, Pune 412114. It was launched in June 2023. It has 150 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
119 of its 150 units are booked (79%). Since the December 2025 update, 29 more units have been booked and the reported concrete structure (RCC) has gone from 65% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.