by Kolte-Patil Developers Limited. Jambhe, Pune 411057. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Oct 2027 – Dec 2028varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
43%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
853 of 1,11976% booked
Price per sq ft
₹9,3002026 salesup 2% on 2025See what buyers paid

Project facts

2 BHK502
3 BHK602
Total units1,119
Buildings7
Land4 acres
Phases2
MahaRERA complaints (filed by or against the builder)2

Since Dec 2025: booked 791 → 853

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 780 sq ft₹68 – 72 lakh2026 sales
3 BHKabout 1,020 sq ft₹92 – 98 lakh2026 sales

Price per sq ft, year by year

2023₹7,800 per sq ft
2024up 10% on 2023₹8,600 per sq ft
2025up 6% on 2024₹9,100 per sq ft
2026up 2% on 2025₹9,300 per sq ft

Registered sales across all 2 phases.

Compared with the typical Jambhe rate in 2026: about 5% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Life Republic Sector R22/22nd Avenue - Atmos Phase - I
Mid-construction
P5210005176562122%68%
Life Republic Sector R22/22nd Avenue - Atmos Phase-II
Mid-construction
P5210005608248369%87%
Show updates by phase

Life Republic Sector R22/22nd Avenue - Atmos Phase - I (P52100051765)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%22%0%434
100%10%0%434
100%0%0%434
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Life Republic Sector R22/22nd Avenue - Atmos Phase-II (P52100056082)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%69%0%419
100%14%0%357
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Life Republic Sector R22 22nd Avenue - Atmos is a project by Kolte-Patil Developers Limited in Jambhe, Pune 411057, registered with MahaRERA as 2 phases (P52100051765, P52100056082). The first phase was launched in June 2023. Together the phases have 1,119 units in 7 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from October 2027 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 43% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

853 of the 1,119 units reported for sale are booked (76%). In 2026 registered sales, 80% of flats here sold at ₹9,300 per sq ft or less (up 2% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Jambhe rate in 2026. Most buyers paid ₹68–72 lakh for 2 BHK flats of about 780 sq ft (2026 sales); ₹92–98 lakh for 3 BHK flats of about 1,020 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension2
Lapsed15
Under construction35
Possession date extended on the builder's application4
Typical time from launch to 100% structure3 years
MahaRERA complaints (filed by or against the builder), all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Source: MahaRERA registrations P52100051765 and P52100056082.Open MahaRERA and search P52100051765All projects in Wakad, Hinjewadi, Marunji