VTP Dolce Vita, Manjari Khurd
by Ashdan Developers Private Limited. Manjari Khurd, Pune 412307. View on Google Maps
- Launched
- First of 4 phases
- Possession dates (MahaRERA)
- Dec 2028 – Jun 2029varies by phaseNo phase has an extended possession date
- Concrete structure (RCC)
- 41%Mid-construction0 of 4 phases with structure completeWeighted across 4 phases
- Units booked
- 1,369 of 1,73779% booked
- Price per sq ft
- ₹11,4002026 salesup 4% on 2025See what buyers paid
Facts
Project facts
| 1 RK | 6 |
|---|---|
| 1 BHK | 52 |
| 2 BHK | 864 |
| 3 BHK | 768 |
| Total units | 1,767 |
| Buildings | 9 |
| Land | 1.1 acres |
| Phases | 4 |
| MahaRERA complaints (filed by or against the builder) | 34 |
Since Dec 2025: booked 1,316 → 1,369
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 1 RK / 1 BHK | about 470 sq ft | ₹41 – 48 lakh | 2024 sales |
| 2 BHK | about 760 – 850 sq ft | ₹94 – 97 lakh | 2026 sales |
| 3 BHK | about 1,090 sq ft | ₹1.23 – 1.44 crore | 2026 sales |
| 4 BHK | about 1,460 – 1,950 sq ft | ₹1.67 – 1.85 crore | 2026 sales |
Price per sq ft, year by year
| 2024 | ₹10,300 per sq ft |
|---|---|
| 2025up 7% on 2024 | ₹11,000 per sq ft |
| 2026up 4% on 2025 | ₹11,400 per sq ft |
Studios (under 450 sq ft): ₹11,800 per sq ft in 2026 sales. Sizes about 260 sq ft.
Registered sales across all 4 phases.
Compared with the typical Manjari Khurd rate in 2026: about 5% lower
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Studios are priced separately from flats and are not used in area price comparisons or on the Property rates page.
Phases
The 4 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| VTP Dolce Vita Phase 1 Mid-construction | P52100051819 | 698 | 46% | 91% | |
| VTP Dolce Vita Phase 2 Mid-construction | P52100055405 | 320 | 33% | 68% | |
| VTP Dolce Vita Phase 3 Mid-construction | P52100055407 | 474 | 38% | 76% | |
| VTP Dolce Vita Phase 4 Mid-construction | P52100055619 | 192 | 44% | 49% |
Show updates by phase
VTP Dolce Vita Phase 1 (P52100051819)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 46% | 0% | 668 | |
| 100% | 5% | 0% | 650 | |
| 100% | 0% | 0% | 583 | |
| 40% | 0% | 0% | 583 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
VTP Dolce Vita Phase 2 (P52100055405)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 33% | 0% | 234 | |
| 100% | 6% | 0% | 218 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
VTP Dolce Vita Phase 3 (P52100055407)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 38% | 0% | 368 | |
| 100% | 10% | 0% | 360 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
VTP Dolce Vita Phase 4 (P52100055619)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 44% | 0% | 99 | |
| 100% | 11% | 0% | 88 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
VTP Dolce Vita is a project by Ashdan Developers Private Limited in Manjari Khurd, Pune 412307, registered with MahaRERA as 4 phases (P52100051819, P52100055405, P52100055407, P52100055619). The first phase was launched in July 2023. Together the phases have 1,767 units in 9 buildings, with 1 RK, 1 BHK, 2 BHK & 3 BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.
The phases' registered possession dates run from December 2028 to June 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 41% complete and final finishes 0% complete. 0 of the 4 phases have their structure complete.
1,369 of the 1,737 units reported for sale are booked (79%). In 2026 registered sales, 80% of flats here sold at ₹11,400 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Manjari Khurd rate in 2026. Most buyers paid ₹41–48 lakh for 1 RK / 1 BHK flats of about 470 sq ft (2024 sales); ₹94–97 lakh for 2 BHK flats of about 760–850 sq ft (2026 sales); ₹1.23–1.44 crore for 3 BHK flats of about 1,090 sq ft (2026 sales); ₹1.67–1.85 crore for 4 BHK flats of about 1,460–1,950 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra. Its studios (under 450 sq ft) sold at ₹11,800 per sq ft or less in 2026; studios are priced separately from flats.
VTP's track record in Pune
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Projects registered with MahaRERA | 70 |
|---|---|
| Completed without extending the possession date | 26 |
| Completed after an extension | 3 |
| Lapsed | 10 |
| Under construction | 31 |
| Possession date extended on the builder's application | 10 |
| Typical time from launch to 100% structure | 4 years 11 months |
| MahaRERA complaints (filed by or against the builder), all VTP projects | 656 (60 of 70 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and July 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.