Skip to main content
← Back

Skyi Manas Lake Phase VIII, Bhukum

Lapsed

by Enerrgia Skyi Ventures LLP. Bhukum, Pune 412115. View on Google Maps

Launched
2 years 10 months promised
Possession date (MahaRERA)
5 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
29%Mid-construction
Units booked
All booked48 units booked

Project facts

2 BHK48
Total units48
Buildings1
Land1.5 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 2 years 10 months have passed
Concrete structure (RCC) 29% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 29%Jun 2025: Concrete structure (RCC) 29%Dec 2025: Concrete structure (RCC) 29%Jul 2026: Concrete structure (RCC) 29%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 29%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%29%0%48
100%29%0%95
100%0%0%67
100%0%0%40

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Skyi Manas Lake Phase VIII (MahaRERA P52100052033) is a residential project by Enerrgia Skyi Ventures LLP in Bhukum, Pune 412115. It was launched in July 2023. It has 48 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in May 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 29% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

All 48 units are booked.

Skyi's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA41
Completed without extending the possession date17
Completed after an extension, or lapsed7
Under construction17
Possession date extended by the builder7
Typical time from launch to 100% structure3 years 4 months
Complaints on MahaRERA, all Skyi projects52 (20 of 41 projects)

See all Skyi projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052033.Check it on MahaRERA (P52100052033)All projects in Bhugaon, Bhukum, Pirangut, Lavale