Town Square, Charholi
Finishing stage
Final finishes 95% · completion not yet filed on MahaRERA
by Krupasindhu Developers. Charholi, Pune 412105. View on Google Maps
- Launched
- 3 years 2 months promised
- Possession date (MahaRERA)
- 1 month agoPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 101 of 15864% booked
Project facts
| 2 BHK | 70 |
|---|---|
| 3 BHK | 48 |
| Other units (shops, offices or not given by type) | 40 |
| Total units | 158 |
| Buildings | 1 |
| Land | 0.8 acres |
| Landowner share | 7 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 81 → 101 · final finishes 85% → 95%
Compared with 6 similar projects in PIN 412105
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 2 mths | 3 yrs 3 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | September 2026 | June 2027 |
| Concrete structure (RCC) complete | 100% | 90% |
| Share of units booked | 64% | 73% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shriram Skypark | July 2023 | June 2027 | 0% | Bookings not reported |
| Matoshri Serenity | June 2023 | December 2028 | 100% | 98 of 134 booked (73%) |
| Sai Darshan | June 2023 | December 2028 | 25% | 58 of 84 booked (69%) |
| Clone Tiara | June 2023 | November 2026 | 100% | 144 of 191 booked (75%) |
| River Nest Building A Wing C | June 2023 | June 2026 | 80% | 166 of 215 booked (77%) |
| Tirupati Eternia Greens | June 2023 | December 2026 | 100% | 125 of 198 booked (63%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 101 | |
| 100% | 100% | 85% | 81 | |
| 100% | 100% | 0% | 11 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Town Square (MahaRERA P52100052087) is a residential project by Krupasindhu Developers in Charholi, Pune 412105. It was launched in July 2023. It has 158 units in 1 building: 118 homes (2 & 3 BHK) and 40 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
101 of its 158 units are booked (64%). Since the December 2025 update, 20 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.