Akshardham Phase 2, Kondhwa Khurd
Finishing stage
Final finishes 90% · completion not yet filed on MahaRERA
by Shreyan Ventures. Kondhwa Khurd, Pune 411048. View on Google Maps
- Launched
- 3 years 4 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 56 of 10056% booked
Project facts
| 1 BHK | 3 |
|---|---|
| 2 BHK | 97 |
| Total units | 100 |
| Buildings | 2 |
| Land | 0.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: booked 39 → 56 · structure 95% → 100% · final finishes 34% → 90% · complaints 0 → 1
Compared with 6 similar projects in PIN 411048
Projects with 50–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 4 mths | 4 yrs 3 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | December 2026 | September 2027 |
| Concrete structure (RCC) complete | 100% | 62% |
| Share of units booked | 56% | 65% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ephelia Phase 2 | July 2023 | December 2028 | 38% | 15 of 78 booked (19%) |
| Prakruti Palladium Phase 2 | June 2023 | March 2027 | 0% | 2 of 98 booked (2%) |
| Advika Phase III - F | June 2023 | March 2028 | 100% | 57 of 87 booked (66%) |
| Siddhigiri | June 2023 | December 2026 | 88% | 142 of 149 booked (95%) |
| Onyx Homes 52 Kondhwa Phase - I | June 2023 | March 2027 | 85% | 56 of 82 booked (68%) |
| Redision Royal | October 2023 | November 2033 | 0% | 106 of 166 booked (64%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 56 | |
| 100% | 95% | 34% | 39 | |
| 100% | 73% | 0% | — | |
| 100% | 60% | 0% | — | |
| 100% | 43% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Akshardham Phase 2 (MahaRERA P52100052307) is a residential project by Shreyan Ventures in Kondhwa Khurd, Pune 411048. It was launched in August 2023. It has 100 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
56 of its 100 units are booked (56%). Since the December 2025 update, 17 more units have been booked and the reported concrete structure (RCC) has gone from 95% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.