Onyx Homes 52 Kondhwa Phase - I, Kondhwa Budruk
by M/s.Onyx Noble Realtors LLP. Kondhwa Budruk, Pune 411048. View on Google Maps
- Launched
- 2 years 9 months originally promised
- Possession date (MahaRERA)
- 5 months awayExtended by 1 year (originally March 2026). Why possession dates change
- Concrete structure (RCC)
- 85%Mid-construction
- Units booked
- 56 of 8268% booked
Project facts
| 2 BHK | 57 |
|---|---|
| Other units (shops, offices or not given by type) | 25 |
| Total units | 82 |
| Buildings | 1 |
| Land | 1.4 acres |
| Landowner share | 7 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 45 → 56 · structure 35% → 85% · possession date March 2026 → March 2027 · total units 88 → 82
Compared with 6 similar projects in PIN 411048
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 9 mths | 4 yrs 3 mths |
| Possession date extended | By 1 year | 0 of 6 |
| Possession date (MahaRERA) | March 2027 | September 2027 |
| Concrete structure (RCC) complete | 85% | 69% |
| Share of units booked | 68% | 34% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Advika Phase III - F | June 2023 | March 2028 | 100% | 57 of 87 booked (66%) |
| Prakruti Palladium Phase 2 | June 2023 | March 2027 | 0% | 2 of 98 booked (2%) |
| Ephelia Phase 2 | July 2023 | December 2028 | 38% | 15 of 78 booked (19%) |
| Sai Arham | August 2023 | December 2026 | 100% | 15 of 30 booked (50%) |
| Akshardham Phase 2 | August 2023 | December 2026 | 100% | 56 of 100 booked (56%) |
| Kool Homes Solitaire Phase III | February 2023 | June 2030 | 0% | 2 of 30 booked (7%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 85% | 0% | 56 | |
| 100% | 35% | 0% | 45 | |
| 100% | 3% | 0% | 45 | |
| 100% | 0% | 0% | 44 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Onyx Homes 52 Kondhwa Phase - I (MahaRERA P52100051595) is a residential project by M/s.Onyx Noble Realtors LLP in Kondhwa Budruk, Pune 411048. It was launched in June 2023. It has 82 units in 1 building: 57 homes (2 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
56 of its 82 units are booked (68%). Since the December 2025 update, 11 more units have been booked, the reported concrete structure (RCC) has gone from 35% to 85% and the possession date has moved from March 2026 to March 2027.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.