Platinum Pride, Katraj

by Shree Mauli Developers · Katraj, Pune 411046 · Map

Launched
Aug 20232 yrs 10 mths originally promised
Possession (MahaRERA)
Mar 2028Extended by 1 yr 9 mths
Concrete structure
100%Nearing possession
Booked
34 of 5463% · 3 in Jul 2026
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
25
Other units
29
Total units
54
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

How construction has progressed

Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Apr 2026Jun 2026Sep 2026Apr 2026: Excavation 100%Jun 2026: Excavation 100%Sep 2026: Excavation 100%Apr 2026: Concrete structure (RCC) 100%Jun 2026: Concrete structure (RCC) 100%Sep 2026: Concrete structure (RCC) 100%Apr 2026: Final finishes 50%Jun 2026: Final finishes 50%Sep 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%
Last 4 updates
Building
UpdateStructureFinishes
Sep 2026100%50%
Jun 2026100%50%
Apr 2026100%50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%34
100%0%0%3
100%0%0%–
100%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹3.6 crore spent · latest estimate ₹6.0 crore · Sep 2026

Latest estimate ₹6.0 croreMar 2024: ₹83 lakh0.8Mar 2024Apr 2026: ₹3.5 crore3.5Apr 2026Jun 2026: ₹3.6 crore3.6Jun 2026Sep 2026: ₹3.6 crore3.6Sep 2026
₹ crore spent

The builder lowered the estimate from ₹6.3 crore to ₹6.0 crore in Sep 2026.

Spent at each update
UpdateSpent
Sep 2026₹3.6 crore
Jun 2026₹3.6 crore
Apr 2026₹3.5 crore
Mar 2024₹83 lakh

Compared with 6 similar projects in PIN 411046

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411046
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths3 yrs 1 mth
Possession date extendedBy 1 yr 9 mths2 of 6
Possession date (MahaRERA)Mar 2028Oct 2026
Concrete structure (RCC)100%100%
Units booked63%36%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Platinum Pride by Shree Mauli Developers is a 54-unit project in Katraj, Pune 411046, launched in August 2023 with possession due in March 2028. 34 units booked out of total 54 units. The concrete structure (RCC) is complete.

Read full summary

Platinum Pride is a project by Shree Mauli Developers in Katraj, Pune 411046, registered with MahaRERA as P52100052347. It was launched in August 2023. It has 54 units in 1 building: 25 homes (2 BHK) and 29 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2028, extended by 1 year 9 months from the original June 2026. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

34 units booked out of total 54 units (63%). Since the July 2026 update, 31 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from June 2026 to March 2028.