Skip to main content
← Back

Durvankur Residency C Wing, Ambegaon Budruk

Lapsed

by Durvankur Developers. Ambegaon Budruk, Pune 411046. View on Google Maps

Launched
1 year 7 months originally promised
Possession date (MahaRERA)
5 months ago. No further extension recordedExtended by 1 year (originally May 2025). What "Lapsed" means
Concrete structure (RCC)
70%Mid-construction
Units booked
24 of 3471% booked

Project facts

2 BHK28
Other units (shops, offices or not given by type)6
Total units34
Buildings1
Land0.5 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 20 → 24 · possession date May 2025 → May 2026

Share on WhatsApp

Compared with 6 similar projects in PIN 411046

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411046
MeasureThis projectSimilar projects
Promised timeline (launch to possession)1 yr 7 mths3 yrs 2 mths
Possession date extendedBy 1 year2 of 6
Possession date passedYes, due May 20261 ready to move; 0 also past their date
Concrete structure (RCC) complete70%100%
Share of units booked71%50%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 1 year 7 months have passed
Concrete structure (RCC) 70% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 25%Jun 2024: Concrete structure (RCC) 50%Dec 2024: Concrete structure (RCC) 60%Jun 2025: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 70%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 70%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%50%24
100%70%50%20
100%60%0%14
100%50%0%6
100%25%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Durvankur Residency C Wing (MahaRERA P52100052822) is a residential project by Durvankur Developers in Ambegaon Budruk, Pune 411046. It was launched in October 2023. It has 34 units in 1 building: 28 homes (2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in May 2026, after an extension of 1 year from the original May 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 70% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.

24 of its 34 units are booked (71%). Since the December 2025 update, 4 more units have been booked and the possession date has moved from May 2025 to May 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052822.Check it on MahaRERA (P52100052822)All projects in Ambegaon, Katraj