Skip to main content
← Back

Amanora Arbano Towers 71 and 72, Hadapsar

by City Corporation Limited. Hadapsar, Pune 411028. View on Google Maps

Launched
4 years 8 months promised
Possession date (MahaRERA)
1 year 7 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 2 buildings
Units booked
225 of 22998% booked

Project facts

1 BHK2
2 BHK94
3 BHK88
4 BHK22
5+ BHK23
Total units229
Buildings2
Land6.5 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 75% → 100% · final finishes 1% → 29%

Share on WhatsApp

Compared with 6 similar projects in PIN 411028

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411028
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 8 mths4 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)May 2028August 2028
Concrete structure (RCC) complete100%88%
Share of units booked98%70%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 1 month of the promised 4 years 8 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 50%Jun 2024: Excavation 83%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 1%Jul 2026: Final finishes 29%Excavation 100%Concrete structure (RCC) 100%Final finishes 29%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%29%225
100%75%1%225
100%0%0%217
83%0%0%—
50%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Amanora Arbano Towers 71 and 72 (MahaRERA P52100052614) is a residential project by City Corporation Limited in Hadapsar, Pune 411028. It was launched in September 2023. It has 229 units in 2 buildings, with 1, 2, 3, 4 & 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is May 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 29% complete. MahaRERA records do not show it as ready to move in.

225 of its 229 units are booked (98%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 75% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052614.Check it on MahaRERA (P52100052614)All projects in Hadapsar, Handewadi