Dosti Greenscapes - Phase 2, Hadapsar

by Dosti Realty Limited. Hadapsar, Pune 411028. View on Google Maps

Launched
4 years 11 months promised
Possession date (MahaRERA)
1 year 6 months awayPossession date unchanged since launch
Concrete structure (RCC)
70%Mid-constructionAverage across 3 buildings
Units booked
151 of 25859% booked
Price per sq ft (incl. balconies and terrace)
₹11,2002026 so far · 62 salesup 3% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK9
3 BHK165
4 BHK84
Total units258
Buildings3
Land1.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 117 → 151 · structure 67% → 70% · final finishes 0% → 30%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,080 sq ft₹1.17 – 1.23 crore
1,400 sq ft₹1.52 – 1.54 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,200 per sq ft63 sales
2025up 7% on 2024₹10,900 per sq ft42 sales
2026 so farup 3% on 2025₹11,200 per sq ft62 sales

Rate vs other Hadapsar projects, 2026: similar

Compared with 5 similar projects in PIN 411028

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411028
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 11 mths4 yrs 9 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)April 2028May 2028
Concrete structure (RCC) complete70%100%
Share of units booked59%96%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 5 months of the promised 4 years 11 months have passed
Concrete structure (RCC) 70% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 27%Jun 2024: Excavation 67%Dec 2024: Excavation 72%Jun 2025: Excavation 72%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 35%Jun 2025: Concrete structure (RCC) 35%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 70%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 70%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%30%151
100%67%0%117
72%35%0%92
67%0%0%48
27%0%0%14

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Dosti Greenscapes - Phase 2 (MahaRERA P52100051041) is a residential project by Dosti Realty Limited in Hadapsar, Pune 411028. It was launched in May 2023. It has 258 units in 3 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 70% complete, final finishes 30% complete. MahaRERA records do not show it as ready to move in.

151 of its 258 units are booked (59%). Since the December 2025 update, 34 more units have been booked and the reported concrete structure (RCC) has gone from 67% to 70%. 80% of the 2026 (so far) sales we found here were at ₹11,200 per sq ft or less (up 3% on 2025), counting balconies and terrace in the size, based on 62 registered sales. Buyers here paid a rate similar to other Hadapsar projects in 2026. Most buyers paid ₹1.17–1.23 crore for flats of 1,080 sq ft and ₹1.52–1.54 crore for 1,400 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100051041.Check it on MahaRERA (P52100051041)All projects in Hadapsar, Handewadi