Akshay Vista, Pimple Gurav
by Akshay Skyscrapers Private Limited. Pimple Gurav, Pune 411061. View on Google Maps
- Launched
- 2 years 7 months originally promised
- Possession date (MahaRERA)
- 7 months awayExtended by 1 year 1 month (originally April 2026). Why possession dates change
- Concrete structure (RCC)
- 85%Mid-construction
- Units booked
- 11 of 5819% booked
Project facts
| 2 BHK | 19 |
|---|---|
| 3 BHK | 35 |
| Other units (shops, offices or not given by type) | 4 |
| Total units | 58 |
| Buildings | 1 |
| Land | 0.6 acres |
| Landowner share | 2 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 0% → 85% · possession date April 2026 → May 2027
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 85% | 0% | 11 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Akshay Vista (MahaRERA P52100052741) is a residential project by Akshay Skyscrapers Private Limited in Pimple Gurav, Pune 411061. It was launched in September 2023. It has 58 units in 1 building: 54 homes (2 & 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is May 2027, extended by 1 year 1 month from the original April 2026. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
11 of its 58 units are booked (19%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 85% and the possession date has moved from April 2026 to May 2027.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.