Skip to main content
← Back

Kamal Galaxy, Yewalewadi

by Raj Properties. Yewalewadi, Pune 411048. View on Google Maps

Launched
4 years 2 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
45%Mid-constructionAverage across 3 buildings
Units booked
22 of 16913% booked

Project facts

1 BHK49
2 BHK105
3 BHK6
Other units (shops, offices or not given by type)9
Total units169
Buildings3
Land1.5 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 4 → 22 · total units 178 → 169

Share on WhatsApp

Compared with 5 similar projects in PIN 411048

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411048
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 2 mths5 yrs 2 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)December 2027December 2028
Concrete structure (RCC) complete45%17%
Share of units booked13%40%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years of the promised 4 years 2 months have passed
Concrete structure (RCC) 45% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 50%Jun 2024: Excavation 67%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 67%Jul 2026: Excavation 67%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 40%Dec 2024: Concrete structure (RCC) 60%Jun 2025: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 45%Jul 2026: Concrete structure (RCC) 45%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 13%Jul 2026: Final finishes 13%Excavation 67%Concrete structure (RCC) 45%Final finishes 13%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%45%13%22
67%45%13%4
100%60%0%4
67%40%0%1
50%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Kamal Galaxy (MahaRERA P52100052832) is a residential project by Raj Properties in Yewalewadi, Pune 411048. It was launched in October 2023. It has 169 units in 3 buildings: 160 homes (1, 2 & 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation 67% complete, structure (RCC) 45% complete, final finishes 13% complete. MahaRERA records do not show it as ready to move in.

22 of its 169 units are booked (13%). Since the December 2025 update, 18 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052832.Check it on MahaRERA (P52100052832)All projects in Kondhwa, Yewalewadi, Pisoli