The Hyphen, Mohammadwadi

by Dynasty AGR Constro LLP. Mohammadwadi, Pune 411048. View on Google Maps

Launched
6 years promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
17%Mid-constructionAverage across 3 buildings
Units booked
58 of 14440% booked

Project facts

3 BHK80
4 BHK40
Other units (shops, offices or not given by type)24
Total units144
Buildings3
Land1.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 17 → 58 · structure 0% → 17%

Share on WhatsApp

Compared with 6 similar projects in PIN 411048

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411048
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs4 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2029December 2028
Concrete structure (RCC) complete17%35%
Share of units booked40%19%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 10 months of the promised 6 years have passed
Concrete structure (RCC) 17% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 60%Dec 2024: Excavation 90%Jun 2025: Excavation 90%Dec 2025: Excavation 90%Jul 2026: Excavation 97%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 17%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 97%Concrete structure (RCC) 17%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
97%17%0%58
90%0%0%17
60%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

The Hyphen (MahaRERA P52100054125) is a residential project by Dynasty AGR Constro LLP in Mohammadwadi, Pune 411048. It was launched in December 2023. It has 144 units in 3 buildings: 120 homes (3 & 4 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 3 buildings: excavation 97% complete, structure (RCC) 17% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

58 of its 144 units are booked (40%). Since the December 2025 update, 41 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 17%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.