Skip to main content
← Back

K City Phase 3, Mundhwa

by Unique Triaa Ventures. Mundhwa, Pune 411036. View on Google Maps

Launched
5 years 2 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
76%Mid-constructionAverage across 5 buildings
Units booked
242 of 25695% booked

Project facts

2 BHK128
3 BHK128
Total units256
Buildings5
Land0.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 131 → 242 · structure 50% → 76% · total units 224 → 256

Share on WhatsApp

Compared with 3 similar projects in PIN 411036

Projects with 100–600 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411036
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 2 mths3 yrs 11 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)December 2028March 2028
Concrete structure (RCC) complete76%100%
Share of units booked95%57%
Complaints on MahaRERA (filed by or against the builder)01

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years of the promised 5 years 2 months have passed
Concrete structure (RCC) 76% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 40%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 60%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 26%Dec 2024: Concrete structure (RCC) 77%Jun 2025: Concrete structure (RCC) 77%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 76%Dec 2023: Final finishes 0%Jun 2024: Final finishes 10%Dec 2024: Final finishes 67%Jun 2025: Final finishes 67%Dec 2025: Final finishes 40%Jul 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 76%Final finishes 40%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%76%40%242
60%50%40%131
100%77%67%131
40%26%10%83
0%0%0%68

"—" means MahaRERA shows no figure for that update.

About this project

K City Phase 3 (MahaRERA P52100052901) is a residential project by Unique Triaa Ventures in Mundhwa, Pune 411036. It was launched in October 2023. It has 256 units in 5 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) 76% complete, final finishes 40% complete. MahaRERA records do not show it as ready to move in.

242 of its 256 units are booked (95%). Since the December 2025 update, 111 more units have been booked and the reported concrete structure (RCC) has gone from 50% to 76%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052901.Check it on MahaRERA (P52100052901)All projects in Mundhwa, Keshavnagar