RKL Shivpuram, Charholi
by Lunkad Vishwa Developers. Charholi, Pune 412105. View on Google Maps
- Launched
- 8 years 2 months promised
- Possession date (MahaRERA)
- 5 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 91%Mid-constructionAverage across 3 buildings
- Units booked
- 77 of 26829% booked
Project facts
| 1 BHK | 93 |
|---|---|
| 2 BHK | 111 |
| 3 BHK | 46 |
| Other units (shops, offices or not given by type) | 18 |
| Total units | 268 |
| Buildings | 3 |
| Land | 2.6 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 48 → 77 · structure 78% → 91% · final finishes 27% → 42%
Compared with 6 similar projects in PIN 412105
Projects with 100–500 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 8 yrs 2 mths | 3 yrs 10 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | December 2031 | August 2027 |
| Concrete structure (RCC) complete | 91% | 64% |
| Share of units booked | 29% | 78% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bliss County Phase 2 | October 2023 | December 2026 | 10% | Bookings not reported |
| Destination Ostia Building E1 | October 2023 | April 2027 | 100% | 93 of 120 booked (78%) |
| Montreal - A-b-c-d | October 2023 | December 2027 | 44% | 431 of 448 booked (96%) |
| Hexa Towers Wing B and C | November 2023 | December 2027 | 85% | 143 of 189 booked (76%) |
| Nexus Gulmohar H | September 2023 | December 2026 | 100% | 165 of 178 booked (93%) |
| Silver Galaxy Phase I | November 2023 | December 2027 | 40% | 176 of 328 booked (54%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 91% | 42% | 77 | |
| 100% | 78% | 27% | 48 | |
| 100% | 40% | 0% | 21 | |
| 40% | 3% | 0% | 3 | |
| 20% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
RKL Shivpuram (MahaRERA P52100053028) is a residential project by Lunkad Vishwa Developers in Charholi, Pune 412105. It was launched in October 2023. It has 268 units in 3 buildings: 250 homes (1, 2 & 3 BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2031, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 91% complete, final finishes 42% complete. MahaRERA records do not show it as ready to move in.
77 of its 268 units are booked (29%). Since the December 2025 update, 29 more units have been booked and the reported concrete structure (RCC) has gone from 78% to 91%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.