Nexus Gulmohar H, Charholi
Finishing stage
Final finishes 95% · completion not yet filed on MahaRERA
by Diamond Nexus Associates. Charholi, Pune 412105. View on Google Maps
- Launched
- 2 years 7 months originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 8 months (originally April 2026). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 165 of 17893% booked
Project facts
| 1 BHK | 15 |
|---|---|
| 2 BHK | 133 |
| 3 BHK | 30 |
| Total units | 178 |
| Buildings | 1 |
| Land | 0.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 128 → 165 · structure 88% → 100% · final finishes 0% → 95% · possession date April 2026 → December 2026
Compared with 5 similar projects in PIN 412105
Projects with 80–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 7 mths | 4 yrs 1 mth |
| Possession date extended | By 8 months | 0 of 5 |
| Possession date (MahaRERA) | December 2026 | December 2027 |
| Concrete structure (RCC) complete | 100% | 40% |
| Share of units booked | 93% | 42% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The Shashwat | September 2023 | December 2026 | 14% | 61 of 206 booked (30%) |
| RKL Shivpuram | October 2023 | December 2031 | 91% | 77 of 268 booked (29%) |
| Hexa Towers Wing B and C | November 2023 | December 2027 | 85% | 143 of 189 booked (76%) |
| Silver Galaxy Phase I | November 2023 | December 2027 | 40% | 176 of 328 booked (54%) |
| Dnyanganga | July 2023 | March 2033 | 25% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 165 | |
| 100% | 88% | 0% | 128 | |
| 100% | 88% | 0% | 86 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Nexus Gulmohar H (MahaRERA P52100052529) is a residential project by Diamond Nexus Associates in Charholi, Pune 412105. It was launched in September 2023. It has 178 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 8 months from the original April 2026. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
165 of its 178 units are booked (93%). Since the December 2025 update, 37 more units have been booked, the reported concrete structure (RCC) has gone from 88% to 100% and the possession date has moved from April 2026 to December 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.