Gangadwar Co-operative Housing Society Limited, Dhankawadi
Lapsed
by Vinod Construction. Dhankawadi, Pune 411043. View on Google Maps
- Launched
- 2 years 2 months promised
- Possession date (MahaRERA)
- 10 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 2 of 366% booked
Project facts
| 1 RK | 1 |
|---|---|
| 1 BHK | 6 |
| 2 BHK | 15 |
| 3 BHK | 14 |
| Total units | 36 |
| Buildings | 1 |
| Land | 0.3 acres |
| Landowner share | 22 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: final finishes 20% → 50%
Compared with 3 similar projects in PIN 411043
Projects with 10–70 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 2 mths | 2 yrs 10 mths |
| Possession date extended | No | 3 of 3 |
| Possession date passed | Yes, due December 2025 | 1 ready to move; 1 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 6% | 45% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nirman Hillside | June 2023 | June 2027 | 100% | 10 of 22 booked (45%) |
| Durga Vihar | December 2022 | June 2026 | 100% | 27 of 40 booked (68%) |
| Dhananjayshree | December 2022 | December 2026 | 100% | 4 of 16 booked (25%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 2 | |
| 100% | 100% | 20% | 2 | |
| 100% | 85% | 0% | 24 | |
| 100% | 35% | 0% | 24 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Gangadwar Co-operative Housing Society Limited (MahaRERA P52100053299) is a residential project by Vinod Construction in Dhankawadi, Pune 411043. It was launched in October 2023. It has 36 units in 1 building, with 1 RK, 1 BHK, 2 BHK & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
2 of its 36 units are booked (6%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.