Skip to main content
← Back

Aaditya Bhairaw, Ravet

by Vakratund Developers. Ravet, Pune 412101. View on Google Maps

Launched
4 years 2 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
25%Mid-constructionAverage across 2 buildings
Units booked
5 of 3714% booked
Price per sq ft (incl. balconies and terrace)
₹7,1002026 so far · 13 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK1
2 BHK36
Total units37
Buildings2
Land0.5 acres
Landowner share1
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: structure 2% → 25% · total units 12 → 37

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
830 – 900 sq ft₹56 – 64 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹7,100 per sq ft13 sales

Rate vs other Ravet projects, 2026: about 20% lower

Compared with 6 similar projects in PIN 412101

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 2 mths2 yrs 4 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)December 2027December 2026
Concrete structure (RCC) complete25%100%
Share of units booked14%60%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years of the promised 4 years 2 months have passed
Concrete structure (RCC) 25% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 2%Jun 2025: Concrete structure (RCC) 2%Dec 2025: Concrete structure (RCC) 2%Jul 2026: Concrete structure (RCC) 25%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 25%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%5
100%2%0%5
100%2%0%3
100%0%0%2
100%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Aaditya Bhairaw (MahaRERA P52100053430) is a residential project by Vakratund Developers in Ravet, Pune 412101. It was launched in October 2023. It has 37 units in 2 buildings, with 1 RK & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 25% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

5 of its 37 units are booked (14%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 2% to 25%. 80% of the 2026 (so far) sales we found here were at ₹7,100 per sq ft or less, counting balconies and terrace in the size, based on 13 registered sales. Buyers here paid a rate about 20% lower than at other Ravet projects in 2026. Most buyers paid ₹56–64 lakh for flats of 830–900 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100053430.Check it on MahaRERA (P52100053430)All projects in Kiwale, Ravet