Skip to main content
← Back

Life Canvas Phase 2, Mamurdi

by Vighnaharta Reality. Mamurdi, Pune 412101. View on Google Maps

Launched
3 years 7 months promised
Possession date (MahaRERA)
8 months awayPossession date unchanged since launch
Concrete structure (RCC)
82%Mid-constructionAverage across 3 buildings
Units booked
175 of 28761% booked

Project facts

1 BHK60
2 BHK159
3 BHK32
Other units (shops, offices or not given by type)36
Total units287
Buildings3
Land3 acres
Landowner share17
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 139 → 175 · structure 45% → 82% · final finishes 0% → 17%

Share on WhatsApp

Compared with 6 similar projects in PIN 412101

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 7 mths4 yrs 1 mth
Possession date extendedNo1 of 6
Possession date (MahaRERA)June 2027December 2027
Concrete structure (RCC) complete82%88%
Share of units booked61%67%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 11 months of the promised 3 years 7 months have passed
Concrete structure (RCC) 82% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 33%Dec 2024: Excavation 50%Jun 2025: Excavation 50%Dec 2025: Excavation 88%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 7%Dec 2024: Concrete structure (RCC) 10%Jun 2025: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 45%Jul 2026: Concrete structure (RCC) 82%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 17%Excavation 100%Concrete structure (RCC) 82%Final finishes 17%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%82%17%175
88%45%0%139
50%10%0%97
33%7%0%43
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Life Canvas Phase 2 (MahaRERA P52100053517) is a residential project by Vighnaharta Reality in Mamurdi, Pune 412101. It was launched in November 2023. It has 287 units in 3 buildings: 251 homes (1, 2 & 3 BHK) and 36 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 82% complete, final finishes 17% complete. MahaRERA records do not show it as ready to move in.

175 of its 287 units are booked (61%). Since the December 2025 update, 36 more units have been booked and the reported concrete structure (RCC) has gone from 45% to 82%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100053517.Check it on MahaRERA (P52100053517)All projects in Kiwale, Ravet