Life Canvas Phase 1, Mamurdi
Finishing stageLapsed
Final finishes 100% · completion not yet filed on MahaRERA
by Vighnaharta Reality. Mamurdi, Pune 412101. View on Google Maps
- Launched
- 3 years 6 months originally promised
- Possession date (MahaRERA)
- 10 months ago. No further extension recordedExtended by 6 months (originally June 2025). What "Lapsed" means
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 237 of 25194% booked
Project facts
| 1 BHK | 124 |
|---|---|
| 2 BHK | 95 |
| 3 BHK | 32 |
| Total units | 251 |
| Buildings | 2 |
| Land | 3 acres |
| Landowner share | 13 |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: final finishes 93% → 100% · complaints 0 → 1
Compared with 6 similar projects in PIN 412101
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 6 mths | 3 yrs 8 mths |
| Possession date extended | By 6 months | 5 of 6 |
| Possession date passed | Yes, due December 2025 | 2 ready to move; 1 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 94% | 68% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 1 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Maheshwaram Majestic | December 2021 | June 2026 | 100% | 63 of 126 booked (50%) |
| City One Skyve | February 2022 | September 2026 | 100% | 327 of 365 booked (90%) |
| Star Vista | October 2021 | April 2025 | 100% | 130 of 150 booked (87%) |
| BG Aspiro | February 2022 | June 2029 | 66% | 164 of 364 booked (45%) |
| Om Mangalam Chaitanya | October 2021 | September 2026 | 100% | 514 of 518 booked (99%) |
| Urban Skyline Phase II | October 2021 | December 2027 | 80% | 296 of 589 booked (50%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 237 | |
| 100% | 100% | 93% | 237 | |
| 100% | 85% | 25% | 248 | |
| 100% | 68% | 0% | 245 | |
| 100% | 30% | 0% | 173 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Life Canvas Phase 1 (MahaRERA P52100032021) is a residential project by Vighnaharta Reality in Mamurdi, Pune 412101. It was launched in December 2021. It has 251 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025, after an extension of 6 months from the original June 2025. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
237 of its 251 units are booked (94%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.