Skip to main content
← Back

Krutika Residency-wing-a, Kasar Amboli

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Parth Properties. Kasar Amboli, Pune 412115. View on Google Maps

Launched
2 years 6 months originally promised
Possession date (MahaRERA)
2 years 2 months awayExtended by 2 years 7 months (originally May 2026). Why possession dates change
Concrete structure (RCC)
100%Finishing stage
Units booked
13 of 1681% booked

Project facts

2 BHK16
Total units16
Buildings1
Land0.3 acres
Landowner share2
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 12 → 13 · possession date May 2026 → December 2028

Share on WhatsApp

Compared with 3 similar projects in PIN 412115

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 412115
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 6 mths3 yrs 1 mth
Possession date extendedBy 2 years 7 months1 of 3
Possession date (MahaRERA)December 2028July 2028
Concrete structure (RCC) complete100%70%
Share of units booked81%53%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 6 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 33%Jun 2024: Excavation 33%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 33%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 100%Jun 2025: Final finishes 100%Dec 2025: Final finishes 100%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%13
100%100%100%12
100%100%100%9
33%33%0%—
33%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Krutika Residency-wing-a (MahaRERA P52100053784) is a residential project by Parth Properties in Kasar Amboli, Pune 412115. It was launched in November 2023. It has 16 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, extended by 2 years 7 months from the original May 2026. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

13 of its 16 units are booked (81%). Since the December 2025 update, 1 more unit has been booked and the possession date has moved from May 2026 to December 2028.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100053784.Check it on MahaRERA (P52100053784)All projects in Bhugaon, Bhukum, Pirangut, Lavale