Floria - 2, Wadgaon Budruk
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Akshay Chintan Builders. Wadgaon Budruk, Pune 411041. View on Google Maps
- Launched
- 4 years 7 months promised
- Possession date (MahaRERA)
- 1 year 9 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 45 of 4992% booked
Project facts
| 2 BHK | 28 |
|---|---|
| 3 BHK | 21 |
| Total units | 49 |
| Buildings | 2 |
| Land | 0.4 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 19 → 45 · final finishes 50% → 100%
Compared with 6 similar projects in PIN 411041
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 7 mths | 3 yrs 8 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | July 2028 | December 2027 |
| Concrete structure (RCC) complete | 100% | 58% |
| Share of units booked | 92% | 54% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Yash Skyline | November 2023 | August 2033 | 100% | 28 of 52 booked (54%) |
| Tridal Samruddhi | January 2024 | September 2026 | 65% | 29 of 41 booked (71%) |
| Divyashree Heights A Wing | March 2024 | December 2027 | 50% | Bookings not reported |
| Madhushree | July 2023 | May 2026 | 100% | 11 of 43 booked (26%) |
| Royal Empire Phase II | May 2024 | December 2027 | 13% | 9 of 28 booked (32%) |
| Park Life Wing D | May 2024 | March 2030 | 0% | 55 of 94 booked (59%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 45 | |
| 100% | 100% | 50% | 19 | |
| 100% | 63% | 0% | 5 | |
| 100% | 63% | 0% | 4 | |
| 75% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Floria - 2 (MahaRERA P52100053930) is a residential project by Akshay Chintan Builders in Wadgaon Budruk, Pune 411041. It was launched in December 2023. It has 49 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
45 of its 49 units are booked (92%). Since the December 2025 update, 26 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.