Skip to main content
← Back

Tridal Samruddhi, Wadgaon Budruk

by M/s. Tridal Associates. Wadgaon Budruk, Pune 411041. View on Google Maps

Launched
2 years 8 months promised
Possession date (MahaRERA)
1 month agoPossession date unchanged since launch
Concrete structure (RCC)
65%Mid-construction
Units booked
29 of 4171% booked

Project facts

1 BHK13
2 BHK28
Total units41
Buildings1
Land0.3 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 25 → 29 · structure 47% → 65%

Share on WhatsApp

Compared with 6 similar projects in PIN 411041

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411041
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 8 mths3 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)September 2026December 2027
Concrete structure (RCC) complete65%75%
Share of units booked71%32%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 2 years 8 months have passed
Concrete structure (RCC) 65% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 62%Jun 2025: Concrete structure (RCC) 62%Dec 2025: Concrete structure (RCC) 47%Jul 2026: Concrete structure (RCC) 65%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 65%Final finishes 0%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%65%0%29
100%47%0%25
100%62%0%—
100%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Tridal Samruddhi (MahaRERA P52100054249) is a residential project by M/s. Tridal Associates in Wadgaon Budruk, Pune 411041. It was launched in January 2024. It has 41 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 65% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

29 of its 41 units are booked (71%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 47% to 65%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100054249.Check it on MahaRERA (P52100054249)All projects in Dhayari