Prism City Yellow, Charholi
Finishing stage
Final finishes 95% · completion not yet filed on MahaRERA
by Swastik Buildtech. Charholi, Pune 412105. View on Google Maps
- Launched
- 2 years originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 1 year (originally December 2025). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 27 of 9030% booked
Project facts
| 3 BHK | 77 |
|---|---|
| 4 BHK | 13 |
| Total units | 90 |
| Buildings | 1 |
| Land | 0.6 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: final finishes 85% → 95% · possession date December 2025 → December 2026
Compared with 6 similar projects in PIN 412105
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs | 3 yrs |
| Possession date extended | By 1 year | 1 of 6 |
| Possession date (MahaRERA) | December 2026 | March 2027 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 30% | 73% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Elica | December 2023 | December 2026 | 100% | 35 of 44 booked (80%) |
| Sanskriti | January 2024 | December 2026 | 100% | 41 of 96 booked (43%) |
| The Butterfly | January 2024 | July 2027 | 100% | 41 of 98 booked (42%) |
| Radhe Windsun | January 2024 | December 2027 | 100% | 106 of 119 booked (89%) |
| Global Serenity- D Building | November 2023 | December 2028 | 61% | 74 of 112 booked (66%) |
| Stella B1 | November 2023 | November 2026 | 100% | 95 of 112 booked (85%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 27 | |
| 100% | 100% | 85% | 27 | |
| 100% | 0% | 0% | 27 | |
| 100% | 0% | 0% | 23 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Prism City Yellow (MahaRERA P52100054020) is a residential project by Swastik Buildtech in Charholi, Pune 412105. It was launched in December 2023. It has 90 units in 1 building, with 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
27 of its 90 units are booked (30%). Since the December 2025 update, the possession date has moved from December 2025 to December 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.