Siddhesh - Yashoda, Kothrud
by Siddhesh Developers Unit - 1. Kothrud, Pune 411038. View on Google Maps
- Launched
- 3 years 10 months promised
- Possession date (MahaRERA)
- 1 year awayPossession date unchanged since launch
- Concrete structure (RCC)
- 90%Mid-construction
- Units booked
- 3 of 437% booked
- Price per sq ft (incl. balconies and terrace)
- ₹13,4002026 so far · 15 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 BHK | 2 |
|---|---|
| 2 BHK | 28 |
| 3 BHK | 13 |
| Total units | 43 |
| Buildings | 1 |
| Land | 0.3 acres |
| Landowner share | 4 |
| Rehab units | 12 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2026 so far | ₹13,400 per sq ft | 15 sales |
|---|
Rate vs other Kothrud projects, 2026: about 20% lower
Compared with 6 similar projects in PIN 411038
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 10 mths | 3 yrs |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | October 2027 | December 2026 |
| Concrete structure (RCC) complete | 90% | 100% |
| Share of units booked | 7% | 39% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shri Keshavlaxmi | December 2023 | March 2028 | 0% | 22 of 52 booked (42%) |
| Anamay Apartments | January 2024 | December 2026 | 100% | 16 of 40 booked (40%) |
| Kirloskar OIL Engine Kaamgar Co Op Housing Society Ltd | January 2024 | December 2027 | 100% | 15 of 52 booked (29%) |
| Manisha Park | November 2023 | December 2026 | 100% | 17 of 34 booked (50%) |
| Anant | November 2023 | December 2026 | 100% | 21 of 60 booked (35%) |
| Meghalaya Apartment Condominium | November 2023 | May 2025 | 100% | 9 of 24 booked (38%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 3 | |
| 100% | 60% | 0% | — | |
| 100% | 0% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Siddhesh - Yashoda (MahaRERA P52100054124) is a residential project by Siddhesh Developers Unit - 1 in Kothrud, Pune 411038. It was launched in December 2023. It has 43 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
3 of its 43 units are booked (7%). 80% of the 2026 (so far) sales we found here were at ₹13,400 per sq ft or less, counting balconies and terrace in the size, based on 15 registered sales. Buyers here paid a rate about 20% lower than at other Kothrud projects in 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.