Mangalam Miraya, Moshi
by Shree Datta Mangalam Associates. Moshi, Pune 412105. View on Google Maps
- Launched
- 3 years 11 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 82%Mid-constructionAverage across 3 buildings
- Units booked
- 265 of 35275% booked
Project facts
| 2 BHK | 182 |
|---|---|
| 3 BHK | 170 |
| Total units | 352 |
| Buildings | 3 |
| Land | 2.2 acres |
| Landowner share | 30 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 77% → 82% · final finishes 3% → 7%
Compared with 6 similar projects in PIN 412105
Projects with 150–800 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 11 mths | 4 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2027 | December 2027 |
| Concrete structure (RCC) complete | 82% | 98% |
| Share of units booked | 75% | 64% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Tanish O2 | January 2024 | March 2028 | 100% | 472 of 482 booked (98%) |
| Wellington F-G | January 2024 | December 2027 | 100% | 267 of 270 booked (99%) |
| Platinum Citylights | February 2024 | December 2027 | 95% | 157 of 240 booked (65%) |
| Ivory Heights | November 2023 | December 2027 | 50% | 244 of 390 booked (63%) |
| Shankeshwar Sparsh | March 2024 | December 2028 | 100% | 211 of 474 booked (45%) |
| Destination Mangalam Marvel | March 2024 | December 2027 | 60% | 322 of 561 booked (57%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 82% | 7% | 265 | |
| 100% | 77% | 3% | 265 | |
| 83% | 32% | 0% | 260 | |
| 53% | 0% | 0% | 83 |
"—" means MahaRERA shows no figure for that update.
About this project
Mangalam Miraya (MahaRERA P52100054359) is a residential project by Shree Datta Mangalam Associates in Moshi, Pune 412105. It was launched in January 2024. It has 352 units in 3 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 82% complete, final finishes 7% complete. MahaRERA records do not show it as ready to move in.
265 of its 352 units are booked (75%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 77% to 82%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.