Skip to main content
← Back

Destination Mangalam Marvel, Charholi

by D R Gavhane Legacy. Charholi, Pune 412105. View on Google Maps

Launched
3 years 9 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
60%Mid-constructionAverage across 5 buildings
Units booked
322 of 56157% booked

Project facts

2 BHK292
3 BHK232
Other units (shops, offices or not given by type)37
Total units561
Buildings5
Land3 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 51% → 60%

Share on WhatsApp

Compared with 6 similar projects in PIN 412105

Projects with 250–1,100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 9 mths4 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2027December 2027
Concrete structure (RCC) complete60%98%
Share of units booked57%86%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 7 months of the promised 3 years 9 months have passed
Concrete structure (RCC) 60% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 30%Dec 2024: Excavation 76%Jun 2025: Excavation 76%Dec 2025: Excavation 80%Jul 2026: Excavation 80%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 7%Jun 2025: Concrete structure (RCC) 7%Dec 2025: Concrete structure (RCC) 51%Jul 2026: Concrete structure (RCC) 60%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 80%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%60%0%322
80%51%0%322
76%7%0%191
30%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Destination Mangalam Marvel (MahaRERA P52100055285) is a residential project by D R Gavhane Legacy in Charholi, Pune 412105. It was launched in March 2024. It has 561 units in 5 buildings: 524 homes (2 & 3 BHK) and 37 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 5 buildings: excavation 80% complete, structure (RCC) 60% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

322 of its 561 units are booked (57%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 51% to 60%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100055285.Check it on MahaRERA (P52100055285)All projects in Charholi, Moshi