Harmony Park, Ravet
by Dream Home Constructions. Ravet, Pune 411044. View on Google Maps
- Launched
- 1 year 9 months originally promised
- Possession date (MahaRERA)
- 1 year awayExtended by 2 years (originally October 2025). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 3 of 2811% booked
Project facts
| 2 BHK | 28 |
|---|---|
| Total units | 28 |
| Buildings | 1 |
| Land | 0.2 acres |
| Landowner share | 11 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: possession date October 2025 → October 2027
Compared with 4 similar projects in PIN 411044
Projects with 10–60 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 1 yr 9 mths | 1 yr 10 mths |
| Possession date extended | By 2 years | 3 of 4 |
| Possession date (MahaRERA) | October 2027 | July 2027 |
| Concrete structure (RCC) complete | 100% | 100% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Paradise Residency | January 2024 | December 2026 | 100% | 10 of 14 booked (71%) |
| Swastik Vyom | November 2023 | December 2025 | 100% | Bookings not reported |
| Vijay Skyline | June 2023 | March 2026 | 100% | 4 of 11 booked (36%) |
| Taara Tower | April 2023 | March 2028 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 3 | |
| 100% | 0% | 0% | 3 | |
| 100% | 0% | 0% | 4 |
"—" means MahaRERA shows no figure for that update.
About this project
Harmony Park (MahaRERA P52100054388) is a residential project by Dream Home Constructions in Ravet, Pune 411044. It was launched in January 2024. It has 28 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2027, extended by 2 years from the original October 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.
3 of its 28 units are booked (11%). Since the December 2025 update, the possession date has moved from October 2025 to October 2027.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.