Micasaa Phase III, Wagholi
by Gagan Global Developers. Wagholi, Pune 412207. View on Google Maps
- Launched
- 4 years 5 months promised
- Possession date (MahaRERA)
- 1 year 8 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 2 buildings
- Units booked
- 89 of 23438% booked
Project facts
| 2 BHK | 233 |
|---|---|
| Other units (shops, offices or not given by type) | 1 |
| Total units | 234 |
| Buildings | 2 |
| Land | 0.4 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 412207
Projects with 100–500 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 5 mths | 4 yrs 6 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | June 2028 | December 2028 |
| Concrete structure (RCC) complete | 0% | 78% |
| Share of units booked | 38% | 85% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Dreams Icon | January 2024 | April 2027 | 100% | 188 of 190 booked (99%) |
| Kharadi Pune P3 | January 2024 | May 2028 | 96% | 93 of 106 booked (88%) |
| Majestique Towers East Phase 6 | November 2023 | December 2028 | 0% | 15 of 192 booked (8%) |
| Equa - Wing D and E | November 2023 | March 2026 | 100% | 116 of 152 booked (76%) |
| Kosmic Kourtyard Phase 2 | March 2024 | December 2028 | 60% | 106 of 130 booked (82%) |
| Flamante by VTP Luxe Phase 2 | March 2024 | June 2029 | 17% | 363 of 396 booked (92%) |
Construction progress
As reported to MahaRERA at each updateWork not started as of Jul 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 89 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Micasaa Phase III (MahaRERA P52100054457) is a residential project by Gagan Global Developers in Wagholi, Pune 412207. It was launched in January 2024. It has 234 units in 2 buildings: 233 homes (2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
89 of its 234 units are booked (38%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.