Skip to main content
← Back

Green Meadows Phase 1, Pachane

Lapsed

by Nandan Rainbow Realties LLP. Pachane, Pune 412115. View on Google Maps

Launched
1 year 4 months originally promised
Possession date (MahaRERA)
4 months ago. No further extension recordedExtended by 1 year (originally June 2025). What "Lapsed" means
Concrete structure (RCC)
100%Nearing possessionAverage across 7 buildings
Units booked
10 of 5120% booked

Project facts

2 BHK1
3 BHK50
Total units51
Buildings7
Land1.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: final finishes 50% → 80%

Share on WhatsApp

Compared with 6 similar projects in PIN 412115

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412115
MeasureThis projectSimilar projects
Promised timeline (launch to possession)1 yr 4 mths3 yrs 10 mths
Possession date extendedBy 1 year0 of 6
Possession date passedYes, due June 20260 ready to move; 0 also past their date
Concrete structure (RCC) complete100%54%
Share of units booked20%42%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 1 year 4 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 18%Dec 2024: Excavation 18%Jun 2025: Excavation 18%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 50%Jul 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%10
100%100%50%—
18%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Green Meadows Phase 1 (MahaRERA P52100054816) is a residential project by Nandan Rainbow Realties LLP in Pachane, Pune 412115. It was launched in February 2024. It has 51 units in 7 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 1 year from the original June 2025. That date has passed and no further extension has been recorded. Construction, averaged across its 7 buildings: excavation complete, structure (RCC) complete, final finishes 80% complete. MahaRERA records do not show it as ready to move in.

10 of its 51 units are booked (20%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100054816.Check it on MahaRERA (P52100054816)All projects in Bhugaon, Bhukum, Pirangut, Lavale