Skip to main content
← Back

Balaji Blossom, Kesnand

by Amit Suresh Shirode. Kesnand, Pune 412207. View on Google Maps

Launched
1 year 3 months originally promised
Possession date (MahaRERA)
8 months awayExtended by 2 years 1 month (originally May 2025). Why possession dates change
Concrete structure (RCC)
95%Mid-construction
Units booked
5 of 1050% booked

Project facts

1 BHK4
2 BHK2
Other units (shops, offices or not given by type)4
Total units10
Buildings1
Land0.1 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 3 similar projects in PIN 412207

Projects with up to 20 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 412207
MeasureThis projectSimilar projects
Promised timeline (launch to possession)1 yr 3 mths1 yr 11 mths
Possession date extendedBy 2 years 1 month2 of 3
Possession date (MahaRERA)June 2027December 2027
Concrete structure (RCC) complete95%88%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 1 year 3 months have passed
Concrete structure (RCC) 95% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 60%Dec 2024: Concrete structure (RCC) 60%Jun 2025: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 95%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 95%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%5
100%60%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Balaji Blossom (MahaRERA P52100054864) is a residential project by Amit Suresh Shirode in Kesnand, Pune 412207. It was launched in February 2024. It has 10 units in 1 building: 6 homes (1 & 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, extended by 2 years 1 month from the original May 2025. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

5 of its 10 units are booked (50%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100054864.Check it on MahaRERA (P52100054864)All projects in Wagholi