Skip to main content

Dolphin Palms, Ravet

by Dolphin Realty. Ravet, Pune 412101. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Mar 2027 – Dec 2029varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
61%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
164 of 23769% booked
Price per sq ft
₹9,2002026 salesup 11% on 2025See what buyers paid

Project facts

1 BHK9
2 BHK182
3 BHK39
Total units237
Buildings5
Land0.8 acres
Phases2

Since Dec 2025: booked 136 → 140

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 560 – 590 sq ft₹43 – 44 lakh2026 sales
2 BHKabout 680 – 760 sq ft₹60 – 70 lakh2026 sales

Price per sq ft, year by year

2024₹8,100 per sq ft
2025up 2% on 2024₹8,300 per sq ft
2026up 11% on 2025₹9,200 per sq ft

Registered sales across all 2 phases.

Compared with the typical Ravet rate in 2026: about 5% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Dolphin Palms Wings C, D and E
Mid-construction
P5210005519717879%79%
Dolphin Palms Wing A and B
Early stage
PM1261012501485520%41%
Show updates by phase

Dolphin Palms Wings C, D and E (P52100055197)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%0%140
100%26%0%136
100%0%0%23
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Dolphin Palms Wing A and B (PM1261012501485)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
65%0%0%24
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 412101

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 6 mths4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2027 – Dec 2029June 2028
Concrete structure (RCC)61%95%
Units booked69%77%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Dolphin Palms is a project by Dolphin Realty in Ravet, Pune 412101, registered with MahaRERA as 2 phases (P52100055197, PM1261012501485). The first phase was launched in March 2024. Together the phases have 237 units in 5 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from March 2027 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 61% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

164 of the 237 units reported for sale are booked (69%). In 2026 registered sales, 80% of flats here sold at ₹9,200 per sq ft or less (up 11% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Ravet rate in 2026. Most buyers paid ₹43–44 lakh for 1 RK / 1 BHK flats of about 560–590 sq ft (2026 sales); ₹60–70 lakh for 2 BHK flats of about 680–760 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100055197 and PM1261012501485.Open MahaRERA and search P52100055197All projects in Kiwale, Ravet