Navyam, Ravet

by Kiwale Realty LLP. Ravet, Pune 412101. View on Google Maps

Launched
5 years 10 months promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 8 buildings
Units booked
118 of 30838% booked
Price per sq ft (incl. balconies and terrace)
₹9,0002026 so far · 65 salesup 3% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK184
3 BHK116
Other units (shops, offices or not given by type)8
Total units308
Buildings8
Land2.3 acres
Reserved units24
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: total units 248 → 308

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
750 – 770 sq ft₹68 – 70 lakh
1,050 sq ft₹88 – 94 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹8,700 per sq ft85 sales
2026 so farup 3% on 2025₹9,000 per sq ft65 sales

Rate vs other Ravet projects, 2026: similar

Compared with 4 similar projects in PIN 412101

Projects with 150–600 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 10 mths3 yrs 2 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)December 2029May 2027
Concrete structure (RCC) complete0%84%
Share of units booked38%62%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 8 months of the promised 5 years 10 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 23%Dec 2024: Excavation 27%Jun 2025: Excavation 27%Dec 2025: Excavation 20%Jul 2026: Excavation 20%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 20%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
20%0%0%118
20%0%0%—
27%0%0%—
23%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Navyam (MahaRERA P52100054888) is a residential project by Kiwale Realty LLP in Ravet, Pune 412101. It was launched in February 2024. It has 308 units in 8 buildings: 300 homes (2 & 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 8 buildings: excavation 20% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

118 of its 308 units are booked (38%). 80% of the 2026 (so far) sales we found here were at ₹9,000 per sq ft or less (up 3% on 2025), counting balconies and terrace in the size, based on 65 registered sales. Buyers here paid a rate similar to other Ravet projects in 2026. Most buyers paid ₹68–70 lakh for flats of 750–770 sq ft and ₹88–94 lakh for 1,050 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.