Swapnapurti Homes, Chikhali
Lapsed
by Ranjit Kantilal Parmar. Chikhali, Pune 411062. View on Google Maps
- Launched
- 2 years 3 months promised
- Possession date (MahaRERA)
- 4 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 5 buildings
- Units booked
- 109 of 13978% booked
Project facts
| 1 BHK | 84 |
|---|---|
| 2 BHK | 55 |
| Total units | 139 |
| Buildings | 5 |
| Land | 0.6 acres |
| Landowner share | 27 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 95 → 109 · structure 0% → 100% · total units 138 → 139
Compared with 4 similar projects in PIN 411062
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 3 mths | 4 yrs 2 mths |
| Possession date extended | No | 1 of 4 |
| Possession date passed | Yes, due June 2026 | 0 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 85% |
| Share of units booked | 78% | 38% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Krystal One Phase IV | April 2024 | December 2027 | 100% | 158 of 222 booked (71%) |
| Mithila Harmony | January 2024 | December 2026 | 100% | 72 of 152 booked (47%) |
| Dwarka Blue Water | June 2024 | May 2031 | 13% | 26 of 296 booked (9%) |
| Lini Homes | October 2023 | December 2029 | 70% | 42 of 143 booked (29%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 109 | |
| 100% | 0% | 0% | 95 | |
| 100% | 0% | 0% | 35 | |
| 80% | 0% | 0% | 51 |
"—" means MahaRERA shows no figure for that update.
About this project
Swapnapurti Homes (MahaRERA P52100055338) is a residential project by Ranjit Kantilal Parmar in Chikhali, Pune 411062. It was launched in March 2024. It has 139 units in 5 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.
109 of its 139 units are booked (78%). Since the December 2025 update, 14 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.