Skip to main content
← Back

Anandam Phase I, Wadgaon

by A V Bhat Developers LLP. Wadgaon, Pune 410507. View on Google Maps

Launched
2 years 8 months originally promised
Possession date (MahaRERA)
1 year 2 months awayExtended by 1 year (originally December 2026). Why possession dates change
Concrete structure (RCC)
15%Mid-constructionAverage across 2 buildings
Units booked
65 of 27624% booked

Project facts

1 BHK166
2 BHK110
Total units276
Buildings2
Land3.4 acres
Landowner share79
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 89 → 65 · structure 0% → 15% · possession date December 2026 → December 2027

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 6 months of the originally promised 2 years 8 months have passed
Concrete structure (RCC) 15% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 0%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 15%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 15%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%15%0%65
100%0%0%89
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Anandam Phase I (MahaRERA P52100055818) is a residential project by A V Bhat Developers LLP in Wadgaon, Pune 410507. It was launched in April 2024. It has 276 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 1 year from the original December 2026. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 15% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

65 of its 276 units are booked (24%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 15% and the possession date has moved from December 2026 to December 2027.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100055818.Check it on MahaRERA (P52100055818)All projects in Talegaon Dabhade, Darumbare