Breeza P II, Mundhwa
by A and A Developers. Mundhwa, Pune 411036. View on Google Maps
- Launched
- 4 years 8 months promised
- Possession date (MahaRERA)
- 2 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 72%Mid-constructionAverage across 3 buildings
- Units booked
- 57 of 11649% booked
Project facts
| 1 BHK | 1 |
|---|---|
| 2 BHK | 80 |
| 3 BHK | 26 |
| Other units (shops, offices or not given by type) | 9 |
| Total units | 116 |
| Buildings | 3 |
| Land | 1.3 acres |
| Reserved units | 12 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 51 → 57 · structure 57% → 72% · total units 75 → 116
Compared with 6 similar projects in PIN 411036
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 8 mths | 4 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2028 | March 2029 |
| Concrete structure (RCC) complete | 72% | 43% |
| Share of units booked | 49% | 58% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mantra Magnus Phase 8 | April 2024 | September 2029 | 38% | 69 of 90 booked (77%) |
| Mantra Magnus Phase 7 | April 2024 | September 2029 | 48% | 49 of 67 booked (73%) |
| Eastern Front | April 2024 | June 2028 | 58% | 27 of 65 booked (42%) |
| Nova Residency | April 2024 | December 2028 | 10% | 49 of 196 booked (25%) |
| Supreme Towers Phase II | May 2024 | June 2029 | 1% | 50 of 123 booked (41%) |
| Anandtara Iris Residences Phase II | March 2024 | December 2026 | 94% | 43 of 52 booked (83%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 72% | 3% | 57 | |
| 67% | 57% | 3% | 51 | |
| 33% | 28% | 0% | 30 | |
| 33% | 4% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Breeza P II (MahaRERA P52100055883) is a residential project by A and A Developers in Mundhwa, Pune 411036. It was launched in April 2024. It has 116 units in 3 buildings: 107 homes (1, 2 & 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 72% complete, final finishes 3% complete. MahaRERA records do not show it as ready to move in.
57 of its 116 units are booked (49%). Since the December 2025 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 57% to 72%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.