Skip to main content
← Back

Sara Nilaay, Nanekarwadi

by Jagrutsara Structures LLP. Nanekarwadi, Pune 410501. View on Google Maps

Launched
6 years 7 months promised
Possession date (MahaRERA)
4 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
68%Mid-constructionAverage across 2 buildings
Units booked
287 of 43067% booked

Project facts

1 BHK402
2 BHK28
Total units430
Buildings2
Land2.4 acres
Landowner share5
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 5% → 68% · final finishes 0% → 25%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 5 months of the promised 6 years 7 months have passed
Concrete structure (RCC) 68% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 0%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 5%Jun 2025: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 68%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 68%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%68%25%287
100%5%0%287
100%5%0%98
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Sara Nilaay (MahaRERA P52100056337) is a residential project by Jagrutsara Structures LLP in Nanekarwadi, Pune 410501. It was launched in May 2024. It has 430 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 68% complete, final finishes 25% complete. MahaRERA records do not show it as ready to move in.

287 of its 430 units are booked (67%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 5% to 68%.

Sara's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA17
Completed without extending the possession date1
Completed after an extension, or lapsed5
Under construction11
Possession date extended by the builder2
Typical time from launch to 100% structure1 year 10 months
Complaints on MahaRERA, all Sara projects0 (0 of 17 projects)

See all Sara projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100056337.Check it on MahaRERA (P52100056337)All projects in Chakan