Osian Almanova, Mundhwa

by Osian Infratech LLP. Mundhwa, Pune 411036. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2029 – Dec 2031varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
0%Early stage0 of 2 phases with structure completeWeighted across 2 phases
Units booked
104 of 13676% booked · 1 phase not reported
Price per sq ft
₹11,7002026 salesup 2% on 2025See what buyers paid

Project facts

3 BHK220
4 BHK52
5+ BHK2
Total units274
Buildings2
Land4 acres
Phases2

Since Dec 2025: booked 4 → 104

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
3 BHKabout 1,060 – 1,310 sq ft₹1.27 – 1.54 crore2026 sales
4 BHKabout 1,660 sq ft₹1.90 – 2.18 crore2026 sales

Price per sq ft, year by year

2025₹11,500 per sq ft
2026up 2% on 2025₹11,700 per sq ft

Registered sales across all 2 phases.

Compared with the typical Mundhwa rate in 2026: about 10% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Osian Almanova Phase 1
Early stage
P521000564921360%76%
Osian Almanova Phase 2
Early stage
PR12600026001751380%Not reported
Show updates by phase

Osian Almanova Phase 1 (P52100056492)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%104
90%0%0%4
10%0%0%4
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Osian Almanova Phase 2 (PR1260002600175)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 5 similar projects in PIN 411036

Projects with 100–600 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 411036
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 7 mths5 yrs 2 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2029 – Dec 2031December 2029
Concrete structure (RCC)0%0%
Units booked76%35%
MahaRERA complaints (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Osian Almanova is a project by Osian Infratech LLP in Mundhwa, Pune 411036, registered with MahaRERA as 2 phases (P52100056492, PR1260002600175). The first phase was launched in June 2024. Together the phases have 274 units in 2 buildings, with 3, 4 & 5+ BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from December 2029 to December 2031; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

104 of the 136 units reported for sale are booked (76%); 1 phase has not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹11,700 per sq ft or less (up 2% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 10% lower than the typical Mundhwa rate in 2026. Most buyers paid ₹1.27–1.54 crore for 3 BHK flats of about 1,060–1,310 sq ft (2026 sales); ₹1.90–2.18 crore for 4 BHK flats of about 1,660 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100056492 and PR1260002600175.Open MahaRERA and search P52100056492All projects in Mundhwa, Keshavnagar