Skip to main content
← Back

Asya, Karve Nagar

Finishing stageLapsed

Final finishes 95% · completion not yet filed on MahaRERA

by Moira Spaces Opc Private Limited. Karve Nagar, Pune 411052. View on Google Maps

Launched
1 year 6 months originally promised
Possession date (MahaRERA)
4 months ago. No further extension recordedExtended by 6 months (originally December 2025). What "Lapsed" means
Concrete structure (RCC)
6%Finishing stage
Units booked
3 of 475% booked

Project facts

4 BHK3
Other units (shops, offices or not given by type)1
Total units4
Buildings1
Land0.1 acres
Landowner share1
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 2 → 3 · final finishes 75% → 95% · possession date December 2025 → June 2026

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 1 year 6 months have passed
Concrete structure (RCC) 6% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 5%Jun 2025: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 6%Jul 2026: Concrete structure (RCC) 6%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 75%Jul 2026: Final finishes 95%Excavation 100%Final finishes 95%Concrete structure (RCC) 6%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%6%95%3
100%6%75%2
100%5%0%1
100%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Asya (MahaRERA P52100066499) is a residential project by Moira Spaces Opc Private Limited in Karve Nagar, Pune 411052. It was launched in June 2024. It has 4 units in 1 building: 3 homes (4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 6 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 6% complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

3 of its 4 units are booked (75%). Since the December 2025 update, 1 more unit has been booked and the possession date has moved from December 2025 to June 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100066499.Check it on MahaRERA (P52100066499)All projects in Karve Nagar