Skip to main content
← Back

Manu, Gultekdi

by Shailesh Fatechand Ranka. Gultekdi, Pune 411037. View on Google Maps

Launched
9 months originally promised
Possession date (MahaRERA)
7 months ago. No further extension recordedExtended by 11 months (originally April 2025). Why possession dates change
Concrete structure (RCC)
100%Nearing possession
Units booked
Bookings not reported

Project facts

3 BHK6
Total units6
Buildings1
Land0.1 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 4 similar projects in PIN 411037

Projects with up to 20 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411037
MeasureThis projectSimilar projects
Promised timeline (launch to possession)9 mths3 yrs 4 mths
Possession date extendedBy 11 months0 of 4
Possession date passedYes, due March 20260 ready to move; 0 also past their date
Concrete structure (RCC) complete100%38%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 9 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 0%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 50%Jun 2025: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Jun 2024: Final finishes 0%Dec 2024: Final finishes 10%Jun 2025: Final finishes 10%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%—
100%50%10%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Manu (MahaRERA P52100076863) is a residential project by Shailesh Fatechand Ranka in Gultekdi, Pune 411037. It was launched in July 2024. It has 6 units in 1 building, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in March 2026, after an extension of 11 months from the original April 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100076863.Check it on MahaRERA (P52100076863)All projects in Gultekdi, Bibwewadi