Skip to main content
← Back

Evexia Imperia, Akurdi

Lapsed

by Evexia Buildcon LLP. Akurdi, Pune 411035. View on Google Maps

Launched
1 year 5 months originally promised
Possession date (MahaRERA)
4 months ago. No further extension recordedExtended by 6 months (originally December 2025). What "Lapsed" means
Concrete structure (RCC)
100%Nearing possession
Units booked
2 of 1414% booked

Project facts

3 BHK14
Total units14
Buildings1
Land0.1 acres
Landowner share7
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 60% → 100% · final finishes 0% → 60%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 1 year 5 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 0%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 25%Jun 2025: Concrete structure (RCC) 25%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 100%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%2
100%60%0%—
100%25%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Evexia Imperia (MahaRERA P52100077056) is a residential project by Evexia Buildcon LLP in Akurdi, Pune 411035. It was launched in July 2024. It has 14 units in 1 building, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 6 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete. MahaRERA records do not show it as ready to move in.

2 of its 14 units are booked (14%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 60% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100077056.Check it on MahaRERA (P52100077056)All projects in Akurdi