Sky 2 Cosmos, Pimple Saudagar
by Emperos Properties. Pimple Saudagar, Pune 411027. View on Google Maps
- Launched
- 1 year 5 months originally promised
- Possession date (MahaRERA)
- This monthExtended by 10 months (originally December 2025). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 9 of 3030% booked
Project facts
| 1 BHK | 30 |
|---|---|
| Total units | 30 |
| Buildings | 2 |
| Land | 0.3 acres |
| Landowner share | 1 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 6 → 9 · structure 40% → 100% · final finishes 0% → 30% · possession date December 2025 → October 2026
Compared with 6 similar projects in PIN 411027
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 1 yr 5 mths | 3 yrs |
| Possession date extended | By 10 months | 1 of 6 |
| Possession date (MahaRERA) | October 2026 | October 2027 |
| Concrete structure (RCC) complete | 100% | 74% |
| Share of units booked | 30% | 31% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sanjog Residency | August 2024 | December 2027 | 40% | 1 of 12 booked (8%) |
| The Arista | May 2024 | August 2027 | 73% | 8 of 31 booked (26%) |
| 7 Cosmos | May 2024 | December 2027 | 75% | 4 of 12 booked (33%) |
| Santiago Sunrise | October 2024 | December 2027 | 100% | 34 of 48 booked (71%) |
| Sai Neel | October 2024 | September 2026 | 0% | 4 of 14 booked (29%) |
| MGP Siddhiksha | January 2024 | December 2026 | 100% | 13 of 30 booked (43%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | 9 | |
| 100% | 40% | 0% | 6 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Sky 2 Cosmos (MahaRERA P52100077156) is a residential project by Emperos Properties in Pimple Saudagar, Pune 411027. It was launched in July 2024. It has 30 units in 2 buildings, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2026, extended by 10 months from the original December 2025. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 30% complete. MahaRERA records do not show it as ready to move in.
9 of its 30 units are booked (30%). Since the December 2025 update, 3 more units have been booked, the reported concrete structure (RCC) has gone from 40% to 100% and the possession date has moved from December 2025 to October 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.