Skip to main content
← Back

Rajveer Garima Phase 1, Wakad

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Waghere Associates. Wakad, Pune 411057. View on Google Maps

Launched
5 years 1 month promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stageAverage across 2 buildings
Units booked
67 of 8876% booked
Price per sq ft (incl. balconies and terrace)
₹11,4002026 so far · 54 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK66
3 BHK22
Total units88
Buildings2
Land2.2 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 24 → 67 · structure 0% → 100% · final finishes 0% → 100%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
840 sq ft₹79 – 96 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹11,400 per sq ft19 sales
2026 so farabout the same as 2025₹11,400 per sq ft54 sales

Rate vs other Wakad projects, 2026: similar

Compared with 4 similar projects in PIN 411057

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 1 mth5 yrs 10 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)December 2029September 2030
Concrete structure (RCC) complete100%20%
Share of units booked76%54%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 11 months of the promised 5 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%67
100%0%0%24
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Rajveer Garima Phase 1 (MahaRERA P52100077863) is a residential project by Waghere Associates in Wakad, Pune 411057. It was launched in November 2024. It has 88 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

67 of its 88 units are booked (76%). Since the December 2025 update, 43 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%. 80% of the 2026 (so far) sales we found here were at ₹11,400 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 54 registered sales. Buyers here paid a rate similar to other Wakad projects in 2026. Most buyers paid ₹79–96 lakh for flats of 840 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100077863.Check it on MahaRERA (P52100077863)All projects in Wakad, Hinjewadi, Marunji