Sky Blue, Kiwale

Finishing stage

Final finishes 95% · completion not yet filed on MahaRERA

by Royal Realty. Kiwale, Pune 412101. View on Google Maps

Launched
9 months originally promised
Possession date (MahaRERA)
7 months ago. No further extension recordedExtended by 6 months (originally September 2025). Why possession dates change
Concrete structure (RCC)
100%Finishing stage
Units booked
14 of 3441% booked

Project facts

2 BHK28
Other units (shops, offices or not given by type)6
Total units34
Buildings1
Land0.3 acres
Landowner share11
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 10 → 14 · final finishes 0% → 95% · possession date September 2025 → March 2026 · total units 22 → 34

Share on WhatsApp

Compared with 6 similar projects in PIN 412101

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)9 mths1 yr 10 mths
Possession date extendedBy 6 months1 of 6
Possession date passedYes, due March 20261 ready to move; 0 also past their date
Concrete structure (RCC) complete100%89%
Share of units booked41%32%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 9 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%14
100%100%0%10
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Sky Blue (MahaRERA P52100078380) is a residential project by Royal Realty in Kiwale, Pune 412101. It was launched in December 2024. It has 34 units in 1 building: 28 homes (2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in March 2026, after an extension of 6 months from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

14 of its 34 units are booked (41%). Since the December 2025 update, 4 more units have been booked and the possession date has moved from September 2025 to March 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100078380.Check it on MahaRERA (P52100078380)All projects in Kiwale, Ravet