Kohinoor Woodshire, Bhugaon

by Intofinity Promoters Private Limited. Bhugaon, Pune 412115. View on Google Maps

Launched
4 years 11 months promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 4 buildings
Units booked
121 of 49325% booked

Project facts

2 BHK284
3 BHK167
4 BHK42
Total units493
Buildings4
Land3.8 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 87 → 121 · total units 420 → 493

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 9 months of the promised 4 years 11 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 84%Jul 2026: Excavation 84%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 84%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
84%0%0%121
84%0%0%87
0%0%0%38
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Kohinoor Woodshire (MahaRERA P52100078709) is a residential project by Intofinity Promoters Private Limited in Bhugaon, Pune 412115. It was launched in January 2025. It has 493 units in 4 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 4 buildings: excavation 84% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

121 of its 493 units are booked (25%). Since the December 2025 update, 34 more units have been booked.

Kohinoor's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA48
Completed without extending the possession date13
Completed after an extension, or lapsed10
Under construction25
Possession date extended by the builder8
Typical time from launch to 100% structure3 years 3 months
Complaints on MahaRERA, all Kohinoor projects52 (19 of 48 projects)

See all Kohinoor projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100078709.Check it on MahaRERA (P52100078709)All projects in Bhugaon, Bhukum, Pirangut, Lavale