Krupa, Shivajinagar
by Kamat Gandhi Venture. Shivajinagar, Pune 411005. View on Google Maps
- Launched
- 3 years 11 months promised
- Possession date (MahaRERA)
- 2 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 20%Mid-construction
- Units booked
- 1 of 911% booked
Project facts
| 3 BHK | 6 |
|---|---|
| 4 BHK | 3 |
| Total units | 9 |
| Buildings | 1 |
| Land | 0.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 0% → 20%
Compared with 5 similar projects in PIN 411005
Projects with up to 20 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 11 mths | 2 yrs 6 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | December 2028 | October 2027 |
| Concrete structure (RCC) complete | 20% | 60% |
| Share of units booked | 11% | 18% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sahavihar | February 2025 | April 2027 | 40% | Bookings not reported |
| Anand Dham | March 2025 | May 2028 | 60% | 3 of 8 booked (38%) |
| Suvarnaban | August 2024 | June 2028 | 85% | 1 of 15 booked (7%) |
| Anahata | July 2025 | October 2027 | 0% | 1 of 12 booked (8%) |
| Buttepatil Capital | June 2024 | December 2026 | 70% | 7 of 26 booked (27%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 20% | 0% | 1 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Krupa (MahaRERA P52100078716) is a residential project by Kamat Gandhi Venture in Shivajinagar, Pune 411005. It was launched in January 2025. It has 9 units in 1 building, with 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
1 of its 9 units is booked (11%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 20%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.